Project implementation period: 2015 – 2018

Employer: Road Infrastructure Agency

It is a design-build project co-financed by the EU Cohesion Fund and the state budget under the Operational Programme “Transport and Transport Infrastructure” 2014-2020, Priority Axis 2 - Development of road infrastructure along the core and comprehensive Trans-European Transport Network.

Struma Lot 3.3 Consortium, in which Patstroy-92 is a partner, completed the project in compliance with FIDIC’s Conditions of Contract – Yellow Book.

Patstroy-92 carried out the following construction and assembly works according to the internal work allocation and responsibilities set out by Struma Lot 3.3 Consortium:

  • excavation works – 460,000 m3
  • fill works – 825,000 m3
  • road base – 105,000 m3
  • strengthening of road foundations – 55,000 m3
  • cement stabilization – 42,000 m3
  • laying 122,000 tons of asphalt mixtures
  • construction of 360 m reinforced embankments
  • 27 culverts
  • 5,000 m stormwater drains

In addition, Patstroy-92 successfully executed demolition of a temporary link on Road I-1 (E79) at km 424+100 on Lot 4 of Struma Motorway and switching of traffic to Lot 3.3 of Struma Motorway. Numerous native trees and shrubs for this area were planted along the motorway and additional 5,200 m2 of turf grassing were sown outside the project.

Struma Motorway is part of the Orient / East-Med TEN-T Core Network Corridor and the shortest route to connect the River Danube and the Aegean Sea, respectively the international ports of Lom and Thessaloniki.

 